Project Overview

Project Type

Infrastructure Expansion

Location

Dorchester County

Owner/Client

SCDOT

Project Start

2023-01-01

Project Completion

2026-08-31

Total Hours Worked

Project Value

$28 Million

Project Size

Berlin G Myers Parkway Phase III

Project Photo Gallery

Project Details

Construction of 7 bridges as a subcontractor to Banks Construction Total Bridge Length 1470 Bridge 1 – Flat slab (5 span) steel pile end bents and intermediate bents Bridge 2 – Flat slab (3 span) steel pile end bents and intermediate bents Bridge 3 – Flat slab (3 span) steel pile end bents and intermediate bents Bridge 4 – Plate girder (3 span continuous) drilled shaft end bents / drilled shaft footer / intermediate bents with PT caps Bridge 5 – Flat slab (8 span) steel pile end bents and intermediate bents Bridge 6 – Flat slab (3 span / 2 stage) drilled shaft end bents / concrete pile intermediate bents Bridge 7 – Flat slab (2 span / 2 stage) steel pile end bents and intermediate bent
View Our

Recent Projects

We’ve been doing this a while, so we have quite a bit to show for it. View all projects or check out one of our latest below.

Questions for us?

Contact The UIG Team Today!