Berlin G Myers Parkway Phase III - Infrastructure Expansion

United Infrastructure group projects

2023

Project Overview

Project Type

Infrastructure Expansion

Location

Dorchester County

Owner/Client

SCDOT

Project Start

2023-01-01

Project Completion

2026-08-31

Aerial view of Berlin G Myers Parkway Phase III construction site overseen by United Infrastructure Group, showcasing vehicles, equipment, and structural developments amidst a wooded area.
Berlin G Myers Parkway Phase III - Infrastructure Expansion

Project Photo Gallery

Project Details

Construction of 7 bridges as a subcontractor to Banks Construction Total Bridge Length 1470 Bridge 1 – Flat slab (5 span) steel pile end bents and intermediate bents Bridge 2 – Flat slab (3 span) steel pile end bents and intermediate bents Bridge 3 – Flat slab (3 span) steel pile end bents and intermediate bents Bridge 4 – Plate girder (3 span continuous) drilled shaft end bents / drilled shaft footer / intermediate bents with PT caps Bridge 5 – Flat slab (8 span) steel pile end bents and intermediate bents Bridge 6 – Flat slab (3 span / 2 stage) drilled shaft end bents / concrete pile intermediate bents Bridge 7 – Flat slab (2 span / 2 stage) steel pile end bents and intermediate bent
View Our

Recent Projects

We’ve been doing this a while, so we have quite a bit to show for it. View all projects or check out one of our latest below.

Questions for us?

Contact The UIG Team Today!

UIG is your trusted partner for bridge and highway construction, maintenance, painting, demolition, expansion, replacement, and rehabilitation in NC, SC, and GA. We proudly serve Charleston, Spartanburg, Fletcher, Charlotte, Lancaster, Orangeburg, and others in these states. Contact the UIG team today. Let’s build stronger bridges and highways together!